{"id":4310,"date":"2026-10-13T13:00:00","date_gmt":"2026-10-13T13:00:00","guid":{"rendered":"https:\/\/lbajiele.com\/?p=4310"},"modified":"2026-10-14T01:52:13","modified_gmt":"2026-10-14T01:52:13","slug":"switchgear-grounding-and-bonding-guide","status":"publish","type":"post","link":"https:\/\/lbajiele.com\/vi\/blog\/switchgear-grounding-and-bonding-guide\/","title":{"rendered":"Switchgear Grounding and Bonding: Interfaces and Verification Records"},"content":{"rendered":"<p>Switchgear grounding and bonding must be coordinated across the supplied assembly, its installed interfaces and the site&#8217;s protective system. Grounding connects the relevant system or equipment to the designated earth arrangement; bonding establishes the required electrical continuity between conductive parts. The exact construction, conductors and verification criteria depend on the installation and applicable requirements. A ground symbol on a drawing or a closed metal cabinet does not prove that every interface has been completed correctly. Buyers should obtain supported equipment details, assign interface responsibilities and retain the inspection and verification records for the actual installation.<\/p>\n<h2>Separate the functions before reviewing the hardware<\/h2>\n<p>Protective grounding and bonding are different from normal circuit-current paths, signal references and the temporary arrangements used during particular work procedures. These terms can be mixed casually in a tender, creating uncertainty about what the supplier is expected to provide. Begin with the system design and identify the function of each relevant conductor and interface. Keep neutral, protective and other connections defined by the actual project requirements rather than treating every earth-related label as interchangeable.<\/p>\n<p>This article is a documentation and procurement guide, not instructions for installing or testing a grounding system. It does not supply conductor sizes, resistance limits or permission to work on energized equipment. Those decisions require qualified engineering and the applicable installation rules. The official electrical references linked below describe their respective U.S. regulatory context; projects elsewhere must use their own applicable requirements and supported equipment instructions. Preserve that jurisdiction and equipment boundary when reviewing a general technical reference.<\/p>\n<h2>Define the supplied assembly boundary<\/h2>\n<p>Ask what grounding and bonding provisions are included in the factory-supplied configuration and what must be completed on site. The boundary can include the enclosure, specified conductive parts and designated interfaces to the installation. Request drawings and instructions for the actual order. Do not infer hidden connections from a photograph or assume that a generic family brochure describes every circuit and accessory fitted to the delivered equipment.<\/p>\n<p>Shipping sections and site assembly can introduce interfaces that require controlled completion. Identify who supplies the necessary parts, who installs them and who records verification. A supplier statement that the assembly has grounding provisions does not mean that the completed installation has been assessed. The acceptance process should connect the factory configuration with the actual site work. This makes missing responsibilities visible before the equipment is energized rather than leaving each contractor to assume that another party completed the interface.<\/p>\n<figure><img decoding=\"async\" alt=\"GGD Low-Voltage Switchgear complete enclosure exterior\" loading=\"lazy\" src=\"https:\/\/lbajiele.com\/wp-content\/uploads\/2026\/10\/switchgear-grounding-and-bonding-guide-body1-20261014.png\" style=\"max-width:100%;height:auto\"\/><figcaption>S\u01a1 \u0111\u1ed3 b\u00ean ngo\u00e0i tham chi\u1ebfu s\u1ea3n ph\u1ea9m \u0111\u1ec3 nh\u1eadn d\u1ea1ng thi\u1ebft b\u1ecb; c\u1ea5u h\u00ecnh v\u00e0 th\u00f4ng s\u1ed1 k\u1ef9 thu\u1eadt y\u00eau c\u1ea7u c\u00e1c t\u00e0i li\u1ec7u k\u00e8m theo.<\/figcaption><\/figure><h2>Review the project system information<\/h2>\n<p>The responsible engineer should provide the system and protective information needed to assess the offered assembly and its connection requirements. The equipment supplier needs the relevant arrangement and site conditions, not merely an instruction to add an earth bar. Confirm what information belongs in the quotation and what must be resolved before manufacturing or installation. Differences between the assumed and actual system should be raised explicitly.<\/p>\n<p>Do not copy an arrangement from another project because the cabinet dimensions or supply voltage appear similar. System conditions and applicable requirements can differ. Keep any protective and neutral interfaces aligned with the approved circuit design. The owner also needs a clear explanation of what later changes would require review. Grounding and bonding records should remain part of the electrical design package rather than becoming an isolated set of marks added to an installation drawing at the end of construction.<\/p>\n<h2>Inspect interfaces through a controlled process<\/h2>\n<p>Prepare an interface register covering the relevant equipment and contractor boundaries. Identify each required connection by its function and drawing reference. Inspection must use authorized access and safe work procedures. This guide does not direct a reader to remove panels, touch conductive parts or perform measurements on an operating assembly. Qualified personnel should determine what access and verification are appropriate for the actual equipment and state.<\/p>\n<p>Record the condition and identity of the interface, not simply a tick saying earth complete. The technical record should make it possible to identify what was inspected and against which approved detail. Where an interface is inaccessible at final acceptance, its earlier completion evidence can be important. Agree these records before installation. A missing inspection record should not be filled retrospectively from memory or replaced by a photograph that cannot establish the relevant connection.<\/p>\n<h2>Use a responsibility and evidence table<\/h2>\n<p>The following qualitative table organizes the coordination work. It is an original checklist rather than a reproduced wiring method or a source of universal acceptance values.<\/p>\n<p>B\u1ed1i c\u1ea3nh tham kh\u1ea3o: <a href=\"https:\/\/www.govinfo.gov\/content\/pkg\/CFR-2025-title29-vol5\/pdf\/CFR-2025-title29-vol5-sec1910-304.pdf\" rel=\"noopener nofollow\" target=\"_blank\">29 CFR 1910.304 grounding and protection, official2025 edition<\/a>. Danh s\u00e1ch ki\u1ec3m tra ch\u1ea5t l\u01b0\u1ee3ng g\u1ed1c n\u00e0y t\u1ed5 ch\u1ee9c c\u00e1c quy\u1ebft \u0111\u1ecbnh c\u1ee7a d\u1ef1 \u00e1n; n\u00f3 kh\u00f4ng ph\u1ea3i l\u00e0 m\u1ed9t ti\u00eau chu\u1ea9n \u0111\u01b0\u1ee3c sao ch\u00e9p ho\u1eb7c thay th\u1ebf cho c\u00e1c ti\u00eau ch\u00ed \u0111\u00e3 \u0111\u01b0\u1ee3c ph\u00ea duy\u1ec7t.<\/p><div class=\"lbaji-table-scroll\" style=\"max-width:100%;overflow-x:auto\"><table style=\"width:100%;border-collapse:collapse\"><thead><tr><th scope=\"col\" style=\"padding:12px;text-align:left;border:1px solid #ddd\">Interface area<\/th><th scope=\"col\" style=\"padding:12px;text-align:left;border:1px solid #ddd\">Information to request<\/th><th scope=\"col\" style=\"padding:12px;text-align:left;border:1px solid #ddd\">Evidence to retain<\/th><\/tr><\/thead><tbody>\n<tr><td style=\"padding:12px;border:1px solid #ddd\">Factory assembly<\/td><td style=\"padding:12px;border:1px solid #ddd\">Included provisions and actual configuration<\/td><td style=\"padding:12px;border:1px solid #ddd\">Supplier drawings and supported instructions<\/td><\/tr>\n<tr><td style=\"padding:12px;border:1px solid #ddd\">Shipping-section joins<\/td><td style=\"padding:12px;border:1px solid #ddd\">Required site-completed interfaces and parts<\/td><td style=\"padding:12px;border:1px solid #ddd\">Installation and inspection record<\/td><\/tr>\n<tr><td style=\"padding:12px;border:1px solid #ddd\">External protective connection<\/td><td style=\"padding:12px;border:1px solid #ddd\">Approved system detail and contractor responsibility<\/td><td style=\"padding:12px;border:1px solid #ddd\">Completed interface verification<\/td><\/tr>\n<tr><td style=\"padding:12px;border:1px solid #ddd\">Doors and removable parts<\/td><td style=\"padding:12px;border:1px solid #ddd\">Supported provisions and maintenance conditions<\/td><td style=\"padding:12px;border:1px solid #ddd\">Inspection and replacement records<\/td><\/tr>\n<tr><td style=\"padding:12px;border:1px solid #ddd\">Cable and enclosure interfaces<\/td><td style=\"padding:12px;border:1px solid #ddd\">Approved entry and conductive-part arrangements<\/td><td style=\"padding:12px;border:1px solid #ddd\">Site completion evidence and deviations<\/td><\/tr>\n<tr><td style=\"padding:12px;border:1px solid #ddd\">Later modifications<\/td><td style=\"padding:12px;border:1px solid #ddd\">Review and re-verification requirements<\/td><td style=\"padding:12px;border:1px solid #ddd\">Revised drawings and technical disposition<\/td><\/tr>\n<\/tbody><\/table><\/div>\n<figure><img decoding=\"async\" alt=\"GGD Low-Voltage Switchgear exterior panel reference view\" loading=\"lazy\" src=\"https:\/\/lbajiele.com\/wp-content\/uploads\/2026\/10\/switchgear-grounding-and-bonding-guide-body2-20261014.png\" style=\"max-width:100%;height:auto\"\/><figcaption>\u0110\u00e2y l\u00e0 h\u00ecnh \u1ea3nh tham kh\u1ea3o b\u00ean ngo\u00e0i \u0111\u1ec3 th\u1ea3o lu\u1eadn v\u1ec1 l\u1ed1i v\u00e0o, giao di\u1ec7n k\u1ebft n\u1ed1i v\u00e0 vi\u1ec7c ki\u1ec3m tra; \u0111\u00e2y kh\u00f4ng ph\u1ea3i l\u00e0 b\u1ea3n v\u1ebd h\u1ec7 th\u1ed1ng \u0111i\u1ec7n ho\u1eb7c h\u1ec7 th\u1ed1ng d\u00e2y \u0111i\u1ec7n.<\/figcaption><\/figure><h2>Treat doors and removable components carefully<\/h2>\n<p>The design may establish particular bonding provisions for doors, covers or removable parts. Ask the manufacturer what is required and how it is maintained. Do not assume that a hinge, painted joint or physical contact supplies the intended continuity without supported design information. Likewise, do not invent a universal bonding strap arrangement for an unknown cabinet. The actual construction and applicable requirements determine the necessary provisions.<\/p>\n<p>Maintenance can change these interfaces. A replaced door, altered cover or removed component should be assessed under the supported instructions. Record the replacement identity and relevant verification rather than relying on visual similarity. The owner should know which features must be restored after access and what constitutes an unresolved defect. This is a practical reason to retain the manufacturer&#8217;s drawings: future personnel should not have to reconstruct the intended connections from the cabinet&#8217;s current appearance.<\/p>\n<h2>Coordinate cable entries and connected metalwork<\/h2>\n<p>Cable and enclosure interfaces require the actual project information and approved installation details. The electrical designer and supplier should identify which conductive parts and connection arrangements belong to the protective system and how completion is verified. Do not leave a contractor to resolve these relationships by drilling a convenient opening or substituting an unfamiliar entry component. Such changes may also affect enclosure protection and the assembly&#8217;s supported construction.<\/p>\n<p>Include interface responsibility in the RFQ and installation scope. A complete equipment package can still arrive without the parts or information needed for a particular site connection if the boundary was never stated. Keep approved deviations and replacement decisions with the final drawings. The owner needs to understand the completed arrangement, including interfaces to associated equipment, rather than receive separate supplier and contractor statements that cannot be reconciled into one installation record.<\/p>\n<h2>Choose verification criteria from the right documents<\/h2>\n<p>Verification should follow an approved plan for the actual installation, with methods and criteria established by the responsible technical parties. The plan should state the boundary, equipment condition, instruments and records required. Do not apply a familiar numerical threshold without confirming what it represents and whether it is appropriate. A single test result does not automatically demonstrate every grounding and bonding function in a complex installation.<\/p>\n<p>Preserve the distinction between inspection, measurement and complete protective-system assessment. Each can provide useful evidence, but they do not answer identical questions. If a result is outside the accepted criterion, obtain a supported technical disposition and retain the corrective and re-verification records. Avoid repeating a measurement until a favourable number appears without explaining the earlier observation. The final record should establish what was accepted and why, not merely present the last result obtained.<\/p>\n<figure><img decoding=\"async\" alt=\"GGD Low-Voltage Switchgear assembly in planned clean environment\" loading=\"lazy\" src=\"https:\/\/lbajiele.com\/wp-content\/uploads\/2026\/10\/switchgear-grounding-and-bonding-guide-body3-20261014.png\" style=\"max-width:100%;height:auto\"\/><figcaption>H\u00ecnh minh h\u1ecda s\u1ea3n ph\u1ea9m v\u1ec1 qu\u00e1 tr\u00ecnh l\u1eafp r\u00e1p trong m\u00f4i tr\u01b0\u1eddng \u0111\u01b0\u1ee3c l\u00ean k\u1ebf ho\u1ea1ch r\u00f5 r\u00e0ng; c\u00e1c th\u00f4ng s\u1ed1 k\u00edch th\u01b0\u1edbc v\u00e0 \u0111i\u1ec1u ki\u1ec7n c\u1ea7n thi\u1ebft s\u1ebd ph\u1ee5 thu\u1ed9c v\u00e0o t\u1eebng d\u1ef1 \u00e1n c\u1ee5 th\u1ec3.<\/figcaption><\/figure><h2>Keep work procedures separate from equipment features<\/h2>\n<p>Grounding and bonding provisions do not eliminate the need to control energy sources and verify the required condition before electrical work. A closed switch, an earth symbol or an external indicator is not a complete work authorization. Qualified personnel must use the procedures for the actual installation and the task. The official work-practice reference below helps distinguish these responsibilities from the construction features supplied with the equipment.<\/p>\n<p>Temporary work-related arrangements, where required, must also be governed by the applicable procedures rather than confused with the permanent protective system. This article deliberately gives no switching or connection sequence. If equipment condition or documentation is uncertain, the responsible authority should assess it before work proceeds. Procurement and handover records can support that assessment by making the intended interfaces and restrictions clear, but a general article cannot establish a safe condition for a specific installed cabinet.<\/p>\n<h2>Maintain traceability after handover<\/h2>\n<p>The final package should connect equipment identity, approved drawings, interface records, verification results and accepted deviations. Keep it searchable by assembly and circuit. Maintenance personnel should be able to find the relevant instructions without relying on a supplier&#8217;s generic product page. Include the process for reviewing changes, so that later cable additions or component replacements do not silently alter an interface on which the original design depends.<\/p>\n<p>Record defects and their closure with enough detail for a future reviewer to understand the decision. Where original documentation is incomplete, seek a supported assessment rather than guessing the arrangement from a similar cabinet. An old label or ground symbol remains physically present after modifications, but its presence does not approve the changed installation. The owner needs a maintained record describing the actual equipment, not a collection of historical documents whose applicability is no longer clear.<\/p>\n<h2>Apply the review to a real procurement request<\/h2>\n<p>The GGD reference images show a real LBAJI low-voltage cabinet exterior. They preserve visible panels and controls without inventing green conductors, earth terminals or an internal connection diagram. The ordered assembly&#8217;s protective interfaces must be established from its actual design and installation documents. Request those details together with the circuit information and site requirements needed by the supplier and engineer.<\/p>\n<p>A useful RFQ names the included provisions, external interfaces, responsible parties and evidence required for acceptance. Compare offers on the same boundary instead of assuming that grounding included means identical scope. The practical result is a coordinated installation record linking the supplied assembly to the site&#8217;s protective system, followed by maintenance arrangements that preserve the approved interfaces. That record is more valuable than an unsupported promise based on cabinet appearance or an isolated numerical result.<\/p>\n<h2>C\u00e1c c\u00e2u h\u1ecfi th\u01b0\u1eddng g\u1eb7p<\/h2>\n<div id=\"rank-math-faq\" class=\"rank-math-block\">\n<div class=\"rank-math-list\">\n<div id=\"faq-20261014-3-1\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Does a metal cabinet prove that bonding is complete?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>No. The actual design, interfaces and completion evidence must establish the required continuity. Exterior appearance is insufficient.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-20261014-3-2\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Can a hinge be assumed to provide the required bonding?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>Not without the supported design and applicable requirements. Ask the manufacturer what provisions must be maintained for the actual door or removable part.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-20261014-3-3\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Is one resistance result a complete protective-system assessment?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>Not automatically. Confirm the purpose, boundary and criteria of each inspection or measurement under the approved verification plan.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-20261014-3-4\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">Can a grounding diagram from another project be reused?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>Only through an appropriate assessment of the actual system, equipment and requirements. Similar appearance or nominal voltage does not establish equivalence.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-20261014-3-5\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question\">What should be handed over to the owner?<\/h3>\n<div class=\"rank-math-answer\">\n\n<p>Provide equipment identities, approved interface drawings, installation and verification records, accepted deviations, maintenance instructions and the process for reviewing later changes.<\/p>\n\n<\/div>\n<\/div>\n<\/div>\n<\/div><h2>Ngu\u1ed3n th\u00f4ng tin k\u1ef9 thu\u1eadt v\u00e0 thi\u1ebft b\u1ecb li\u00ean quan<\/h2><p>C\u00e1c trang danh m\u1ee5c ti\u00eau chu\u1ea9n x\u00e1c \u0111\u1ecbnh ph\u1ea1m vi t\u00e0i li\u1ec7u; vi\u1ec7c tu\u00e2n th\u1ee7 v\u00e0 ch\u1ea5p nh\u1eadn y\u00eau c\u1ea7u c\u00e1c t\u00e0i li\u1ec7u \u0111\u1ea7y \u0111\u1ee7 \u00e1p d\u1ee5ng v\u00e0 vi\u1ec7c \u0111\u00e1nh gi\u00e1 k\u1ef9 thu\u1eadt d\u1ef1 \u00e1n.<\/p><ul><li><a href=\"https:\/\/www.govinfo.gov\/content\/pkg\/CFR-2025-title29-vol5\/pdf\/CFR-2025-title29-vol5-sec1910-304.pdf\" rel=\"noopener nofollow\" target=\"_blank\">29 CFR 1910.304 grounding and protection, official2025 edition<\/a><\/li><li><a href=\"https:\/\/www.govinfo.gov\/content\/pkg\/CFR-2025-title29-vol5\/pdf\/CFR-2025-title29-vol5-sec1910-333.pdf\" rel=\"noopener nofollow\" target=\"_blank\">29 CFR 1910.333 v\u1ec1 c\u00e1c quy tr\u00ecnh l\u00e0m vi\u1ec7c trong ng\u00e0nh \u0111i\u1ec7n, phi\u00ean b\u1ea3n ch\u00ednh th\u1ee9c n\u0103m 2025<\/a><\/li><li><a href=\"https:\/\/webstore.iec.ch\/en\/publication\/30043\" rel=\"noopener nofollow\" target=\"_blank\">IEC 61439-2 power switchgear and controlgear assembly scope<\/a><\/li><li><a href=\"https:\/\/lbajiele.com\/vi\/san-pham\/ggd-low-voltage-switchgear\/\" rel=\"noopener\">LBAJI GGD Thi\u1ebft b\u1ecb chuy\u1ec3n m\u1ea1ch \u0111i\u1ec7n \u00e1p th\u1ea5p<\/a><\/li><li><a href=\"https:\/\/lbajiele.com\/vi\/blog\/complete-guide-to-switchgear-fundamentals-comparisons\/\" rel=\"noopener\">Nh\u1eefng nguy\u00ean t\u1eafc c\u01a1 b\u1ea3n v\u1ec1 thi\u1ebft b\u1ecb \u0111i\u1ec1u khi\u1ec3n<\/a><\/li><li><a href=\"https:\/\/lbajiele.com\/vi\/blog\/switchgear-testing-testing-guide\/\" rel=\"noopener\">Ki\u1ec3m tra v\u00e0 th\u1eed nghi\u1ec7m thi\u1ebft b\u1ecb chuy\u1ec3n m\u1ea1ch<\/a><\/li><li><a href=\"https:\/\/lbajiele.com\/vi\/blog\/switchgear-maintenance-checklist-maintenance-guide\/\" rel=\"noopener\">Danh s\u00e1ch ki\u1ec3m tra b\u1ea3o tr\u00ec thi\u1ebft b\u1ecb chuy\u1ec3n m\u1ea1ch<\/a><\/li><\/ul><h2>Ti\u1ebfp t\u1ee5c h\u1ecdc t\u1eadp: ch\u1ee9c n\u0103ng c\u1ee7a thi\u1ebft b\u1ecb<\/h2><p>Gi\u00e1o tr\u00ecnh gi\u00e1o d\u1ee5c \u0111\u1ed9c l\u1eadp n\u00e0y gi\u1ea3i th\u00edch v\u1ec1 c\u01a1 s\u1edf thi\u1ebft b\u1ecb. N\u00f3 kh\u00f4ng tr\u00ecnh b\u00e0y quy tr\u00ecnh l\u00e0m vi\u1ec7c an to\u00e0n cho qu\u00e1 tr\u00ecnh l\u1eafp r\u00e1p c\u1ee5 th\u1ec3. Ngu\u1ed3n: Gaurav J \u2013 TheElectricalGuy.<\/p><div data-video-title=\"Switchgear Basics: Complete Beginner's Guide | TheElectricalGuy\" onclick='var w=this;setTimeout(function(){var f=w.querySelector(\"iframe\");if(f){f.title=w.getAttribute(\"data-video-title\");f.loading=\"lazy\";}},100);' style=\"position:relative;width:100%;padding-top:56.25%\"><iframe allowfullscreen=\"\" loading=\"lazy\" src=\"https:\/\/www.youtube-nocookie.com\/embed\/1eLEa9uqE3k\" style=\"position:absolute;top:0;left:0;width:100%;height:100%;border:0\" title=\"Nh\u1eefng \u0111i\u1ec1u c\u01a1 b\u1ea3n v\u1ec1 thi\u1ebft b\u1ecb \u0111i\u1ec7n: H\u01b0\u1edbng d\u1eabn d\u00e0nh cho ng\u01b0\u1eddi m\u1edbi b\u1eaft \u0111\u1ea7u | TheElectricalGuy\"><\/iframe><\/div><p><a href=\"https:\/\/www.youtube.com\/watch?v=1eLEa9uqE3k\" rel=\"noopener nofollow\" target=\"_blank\">Xem video Gi\u1edbi thi\u1ec7u v\u1ec1 thi\u1ebft b\u1ecb chuy\u1ec3n m\u1ea1ch: H\u01b0\u1edbng d\u1eabn d\u00e0nh cho ng\u01b0\u1eddi m\u1edbi b\u1eaft \u0111\u1ea7u | TheElectricalGuy<\/a><\/p>","protected":false},"excerpt":{"rendered":"<p>Switchgear grounding and bonding must be coordinated across the supplied assembly, its installed interfaces and the site&#8217;s protective system. Grounding connects the relevant system or equipment to the designated earth ar<\/p>","protected":false},"author":6,"featured_media":4303,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[58],"tags":[83,88,75],"class_list":["post-4310","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-electrical-engineering-guides","tag-power-distribution","tag-procurement-rfq","tag-switchgear"],"blocksy_meta":[],"acf":[],"_links":{"self":[{"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/posts\/4310","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/users\/6"}],"replies":[{"embeddable":true,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/comments?post=4310"}],"version-history":[{"count":2,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/posts\/4310\/revisions"}],"predecessor-version":[{"id":4318,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/posts\/4310\/revisions\/4318"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/media\/4303"}],"wp:attachment":[{"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/media?parent=4310"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/categories?post=4310"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/lbajiele.com\/vi\/wp-json\/wp\/v2\/tags?post=4310"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}